Correct installation method and instructions of spray filling machine
Date: 2024-09-10Read: 5
Correct installation method and instructions of spray filling machine
Spray filling machine is a commonly used type of filling machine. Many customers will ask about its installation method and instructions. Let's learn about it together.
Correct installation method of spray filling machine:
1. Take out the air filtration pressure regulating valve of the aerosol filling machine from the filling machine cabinet and install it on the right side panel on the front of the cabinet. Unscrew the binary oil cup and fill it with lubricating oil up to the horizontal line, about 20ml. Do not fill it up.
2. Push the compressed air pipe into the inlet of the duplex (after the air compressor outlet valves of the 08 and 10 battalions are opened, adjust the two knobs on the top of the duplex. The right knob is for pressure adjustment. When adjusting, lift the screw carefully, rotate clockwise to increase the pressure, rotate clockwise to reduce the pressure, and adjust the pressure at 0.3-0.4npa13-4 kg/C ㎡). The right knob is for the adjustment of the lubricating oil inlet, which can be properly rotated left and right according to the oil consumption. Generally, a cup of oil will be used up in 10-15 working days and then added.
3. Check whether the electrical parts and connectors of the spray filling machine are firm. Connect the power supply to 220V and connect the grounding wire to ensure safety. The working voltage of this machine is the safe voltage DC 24V.
4. Place the foot switch in front of the filling machine workbench, and the foot will work once. If the foot is not loosened, the equipment will continue to work.
5. Connect the oil inlet pipeline, connect it with a steel wire hose, wrap the interface with sealing tape, and tie it tightly with steel wire to prevent air leakage. It is not allowed to install filtering equipment on the pipeline.
6. Adjust the metering magnetic switch of the spray filling machine to the corresponding filling position, subject to the upper end of the magnetic switch, and then fill the test for several times until the air in the pipeline is completely discharged.
7. After installation, it is necessary to carefully and repeatedly debug the installation machine to ensure the weight of the filled product. If necessary, it can be adjusted to a certain scale for fixation. This way, in the future use, there will be no need to frequently adjust the scale and filling degree, which provides convenience for the operation and use of the equipment.
Instructions for use of spray filling machine
1. Before driving, you must first use the joystick to rotate the machine and check if there is any abnormality in its rotation. Only after confirming that it is normal can you start driving.
2. Because the spray filling machine is an automatic machine, the sizes of easy to pull bottles, bottle mats and bottle caps are required to be uniform
3. When adjusting the machine, tools should be used appropriately. It is strictly prohibited to use excessive tools or force to disassemble parts to avoid damaging the components or affecting the performance of the machine.
4. Whenever the spray filling machine is adjusted, the loosened screws must be tightened, and the machine can be started only after turning the machine with a crank handle to check whether its action meets the requirements,
5. The spray filling machine must be kept clean, and it is strictly prohibited to have oil stains, liquid medicine or glass debris on the machine, so as not to cause corrosion of the spray filling machine. Therefore, it is necessary to: during the production process of the spray filling machine, remove the liquid medicine or broken glass eyebrows in a timely manner. Before the shift, clean all parts of the machine surface, add clean lubricating oil to each activity department, and wash it once a week, especially wipe or blow with compressed air the places that are not easy to clean in normal use.